Rainwater Harvesting System & Average Annual Rainwater Collection and Usage
Most of the building at UMPSA equipped with Rainwater Harvesting System for general purposes and plant irrigation.
No. |
Year Installed |
Location |
Tank Capacity (gallons) |
Tank Qty |
Total tank capacity (gallons) |
Total tank capacity (m³) - A |
Rooftop collection area (m³) |
Minimun tank size for maximum collection (St=0.01m2 x roof area in m³) |
Average annual rainwater Yield (m³) - AARY for Kuantan = 111 |
Average annual rainwater yield (m3) - AARY FOR Kuantan =111 (UMPSA tank (A) |
1 |
2016 |
Staff Quarters (40 unit) |
20 |
10 |
200 |
0.91 |
122 |
1.22 |
135 |
101.01 |
2 |
2016 |
Paddle House |
90 |
1 |
90 |
0.4095 |
361 |
3.61 |
401 |
45.4545 |
3 |
2017 |
Nursery |
90 |
1 |
90 |
0.4095 |
143 |
1.43 |
159 |
45.4545 |
4 |
2018 |
Orchard |
500 |
3 |
1500 |
6.825 |
82 |
0.82 |
91 |
757.575 |
5 |
2017 |
Musolla, Lake C |
200 |
1 |
200 |
0.91 |
122 |
1.22 |
135 |
101.01 |
6 |
2018 |
Teching Factory |
350 |
1 |
350 |
1.5925 |
720 |
7.2 |
799 |
176.7675 |
7 |
2019 |
Compose Site, Landscape Office |
500 |
1 |
500 |
2.275 |
153 |
1.53 |
170 |
252.525 |
8 |
2022 |
Canseleri Tun Abdul Razak, Faculty of Electrical and Electronics Engineering Technology, Multipurpose Hall, Faculty of Computing, Landscape Office, Centre for Property Management and Development |
20 |
10 |
200 |
0.91 |
200 |
2.00 |
222 |
101.01 |
9 |
2023 |
UMPSA Mosque |
|
1 |
1000 |
4.55 |
150 |
1.5 |
167 |
505.05 |
Total |
|
29 |
4130 |
18.79 |
2053 |
20.53 |
2279 |
2086 |
Rainwater Harvesting installation at UMPSA |
Rainwater Collection Location
Location of Tank Rain Harvesting at UMPSA
Building: Bioaromatic |
Capacity: 20 Gallon |
Surau Lake |
WATER IRRIGATION PUMP SYSTEM
Water used for watering plant using pump system.
|
|
|
|
|
M3 PER QUARTER |
|
||||
LAKE SOURCE |
Pump Flow Rate (m3/hr) |
Hour Used Per Day for watering |
Estimation m3 per day |
m3 per month |
Q1 |
Q2 |
Q3 |
Q4 |
Total M3/year |
|
LAKE D |
3.6 |
4 |
14.4 |
432.00 |
1,296 |
1,296 |
1,296 |
1,296 |
5,184 |
|
LAKE B |
70 |
4 |
280 |
8,400.00 |
2024 – re-arrange to other new planting project |
|||||
LAKE A |
58 |
4 |
232 |
6,960.00 |
20,880 |
20,880 |
20,880 | 20,880 |
83,520 |
|
TOTAL |
|
|
526.4 |
15,792.00 |
22,176 |
22,176 |
22,176 | 22,176 |
66,528 |
Table 4.2: List of pump system for watering plant at UMPSA
Total Water Recycle (M3) |
68,109.00 |
Total Water Treated Water (M3) (Pekan & Gambang) |
1,428,452.00 |
% Water Recycle |
4.77% |
Pump system at Lake D |
Pump system at Lake B |
New developed water pump at Lake A to supply water for watering system at the neareast tree planting area and landscaping projects. |
Water Ablution Recycle Concept
Water Recycling Program- Recycled Water Ablution System at Masjid UMPSA Gambang Campus- This project is a part of water recycling program. The recycled water ablution system with filtration will be installed at Masjid UMPSA Gambang Campus. The recycled water will be used to water the UMPSA nursery plant.
Water Ablution Recycle System Diagram |
Ground Water
UMPSA’s Gelatin Incubator are equiped with underground water sources. This water are using to use for operation of the Gelatin Halal Incubator Project.
Water System Treatment Tank |