Solar Installation Plan
SOLAR INSTALLATION PLAN
Solar installation plan is one of the UMP initiatives in reducing overall energy consumption in line with the Pelan Kampus Lestari and Long-Term Green Campus Blueprint. The duration of this initiative is 15 September 2020 to 30 June 2021.
Benefits of Solar Installation to UMP:
- Installed by NEM (Net Energy Metering), where TNB will buy the energy generated at RM 0.36 per kw/h (1: 1).
- Proposed installation on the ground and roof of the walkway at on campus.
- 5,000 students will enjoy this renewable energy, as university savings, income generation and even a place to students and staff study and study solar technology.
- Improve the ranking of the Green Matrix UI.
- Reduction of carbon dioxide emissions to the environment.
- Long -term income generation
Summary of the project:
Solar Installation Capacity: 4.2 MWp
Location: parking area, walkway, roof
Installation Cost: RM2.5mil/MW
Duration: 10 months
Project Implementation: Usahasama Swasta dan Agensi UMP; Dekad Aliran Sdn. Bhd; Yayasan UMP